RFT 2022-71 Lees Road Rehabilitation

Provide for the complete rehabilitation of Lee’s Road including frost heave construction; full depth reclamation (pulverizing); culvert replacement; binder and surface paving; asphalt gutter with side
outlets; Granular A shouldering; ditching; Safence three cable guide system; rip rap installation; erosion and sediment control devices; restoration of all disturbed areas and other ancillary items.

Project Area
Project Limits
GiS Area Map
Area Mapping

Timeline

Key Dates

Monday July 04 2022
Issue Date of RFT

The City will only consider Bids received from Bidders who have registered with the City’s electronic bidding system at https://cityofnorthbay.bidsandtenders.ca (the “Bidding System”) and have obtained the RFT directly from the Bidding System.
Location City Hall

Tuesday July 12 2022
Deadline for Questions

Friday July 15 2022
Deadline for Issuing Addenda

Tuesday July 19 2022
Submission Deadline

Wednesday August 10 2022
Anticipated Execution of Agreement

Related Documents

Contacts

Gerry McCrank, C.E.T., LEL

Senior Project Manager gerry.mccrank@northbay.ca (705) 474-0400 ext. 2305