North Bay, ON – June 1, 2021 – Installation of a new sewage pumping station and sanitary sewer on Wallace Road is expected to begin June 14.
The work involves the construction of a new sewage pumping station adjacent to Optimist Park on Wallace Road and the installation a new sanitary sewer that will run from the location of the existing pumping station, across from Bavarian Meat Products, to the new site. A new forcemain will also be installed, which will run to from the new pumping station to a sanitary sewer outlet at the intersection of Wallace and Lake Heights roads.
Wallace Road will be reduced to one lane between Commerce Court and Lake Heights Road using temporary traffic control lights for an extended period during construction.
The $2.7-million project will be completed over two construction seasons with the installation of the sanitary sewer and forcemain, as well as road reconstruction slated for 2021. The remainder of the project will be completed in 2022, with the new pumping station to be commissioned and the old pumping station to be removed in June of 2022.
The contractor will make every effort to limit the extent of noise and disruptions during this project. The City of North Bay thanks residents for their patience while this important infrastructure work is completed.
WHAT TO EXPECT ONCE CONSTRUCTION BEGINS:
Work Hours |
Work on this project will occur Monday to Friday from 7:00am until 7:00pm. During various operations the contractor will be permitted to work on Saturdays with proper notice. Working on Sundays is not permitted without special permission. |
Traffic Management |
Traffic will be reduced to one lane using temporary traffic control lights on Wallace Road during installation of sewers, forcemain and road construction. Motorists are reminded to abide by traffic/construction signs posted in local areas to ensure safe travel of all users including pedestrians and bicycle riders. Every effort will be made to manage traffic and closures for the safety of construction workers, pedestrians and residents. Road users should expect delays travelling through this section for the duration of the project. |
Parking |
Parking will not be permitted anywhere on Wallace Road between Lake Heights Road and Commerce Crescent especially in those areas of active construction work. Temporary parking arrangements will be provided by the contractor to those residents who cannot enter their driveway due to location of underground infrastructure installation or road construction.
|
Pedestrians |
Pedestrians are encouraged to travel along the edges of the right-of-way and designated areas provided by the contractor. |
Deliveries |
Deliveries may occur during construction using local access but may not always be possible due to the location of installing infrastructure. The Contractor will make every effort to assist with delivery of your packages. |
Residents |
Residents along Wallace Road will have access to their property at all times except when various restrictions occur (construction of various infrastructures in the area of their residence). The Contractor will assist with picking up your garbage and recyclables placed in front of the residence and delivering to the collection agency on the day of normal schedule pick-up. |
Businesses |
All businesses’ access will remain open during the construction with signage placed at both the ends of the construction limits on Wallace Road as necessary. The Contractor will assist with picking up your garbage and recyclables placed in front of the business and delivering to the collection agency on the day of normal schedule pick-up. |