North Bay, ON – August 21, 2025
Rehabilitation to the intersection of Lakeshore Drive and Marshall Park Drive are set to begin in mid-September and will be completed by mid-November 2025. The scope of work includes the removal of the existing traffic control equipment and above grade infrastructure and installation of new traffic and pedestrian control signals, curb & gutter, concrete sidewalks, tactile crossing plates, asphalt boulevard and resurfaced asphalt intersection.
One lane of traffic in all directions will be maintained throughout the project to provide access to local properties and ensure safe travel through the construction zone. Short traffic delays may be required at times to complete underground infrastructure work, including electrical duct installation, asphalt pulverizing, installation of curb and gutter and surface paving.
Further notices with additional project information will be provided by the contractor, Pioneer Construction Inc., ahead of construction.